Kingsville Begins Three Phases of Roadwork on Division Road North

Posted On Wednesday July 13, 2022

The Town of Kingsville has begun the first three phases of roadwork on Division Road North from Water Street to Palmer Drive.

The first phase consists of curb, manhole and catch-basin repairs. During this operation, during daytime hours, a lane of traffic may be shifted, or flaggers may control alternating traffic. This work began today (July 13, 2022) and will last up to two weeks. 

Phase two begins in late July and consists of removing the existing asphalt and paving the base asphalt.

Phase three consists of paving surface asphalt and painting lines. 

During these phases, Division Road North will be reduced to a single lane of alternating traffic, controlled by flaggers, and at times, access to side streets may be restricted for short periods. Drivers should expect delays or avoid the area when possible.

The Town anticipates all work to be complete in August.